Operating-mine implementation
SMART was successfully implemented underground at Madero.
At Peñoles’ Francisco I. Madero mine in Zacatecas, Mexico, the program built a 30-room engineered top slice and mined the first lower lift beneath its reinforced roof at production dimensions.
Patented • successfully implemented at production dimensions
30rooms
30posts
~2,000 m²continuous reinforced floor
~100 munder-roof development
15 mpanel opened
Intactengineered system
The program constructed the engineered floor, installed the posts and advanced beneath the reinforced system using mine equipment and site materials.